I ran across an interesting issue recently and I wanted to share the solution.á I am currently working on a fairly large project.á We have had a turbulent start and I was not able to baseline my project plan before my developers began working on their tasks.á I knew that from a schedule standpoint we were hosed, but other Earned Value calculations should still be ok.á I baselined my project plan but discovered an issue.á When I refereshed my project plan from TFS, all of the baselines were wiped out because 0's were stored in TFS! The fix turned out to be easy.á Here is what I did:
  1. I used the tfsfieldmapping.exe to download the field mappings for MS Project.
  2. Iáremoved the field mapping for the baseline field and uploaded the new mappings to project.
  3. I refreshed my project plan to collected the hours entered by my developers.
  4. I added the field mapping for Baseline back into the MS Project field mappings.
  5. I published the Projectáback to TFS with the baselines.
Hope this helps you sometime. Happy Coding! Posted on Wednesday, September 27, 2006 9:09 PM Administration | Back to top


Comments on this post: Oh no! I have hours on Team System Tasks but No Baseline!

No comments posted yet.
Your comment:
 (will show your gravatar)


Copyright © Mike Azocar | Powered by: GeeksWithBlogs.net