Geeks With Blogs
Saqib Ullah BootStrapper Know How
Dubai: The Dh3.67 billion Burj Dubai tower hit the light-headed heights of 75 levels this week. Currently going up at one level every three days, approximately 125 floors remain to built. Tower will be completed in 2008. Since construction began in January 2005, 216,000 cubic metres of concrete and 39,700 metric tonnes of reinforced steel have been used. Approximately 3,000 workers in total are currently working on-site. Still to go 125 floors. Posted on Friday, October 27, 2006 2:57 AM General | Back to top


Comments on this post: 75 floors

No comments posted yet.
Your comment:
 (will show your gravatar)


Copyright © Saqib Ullah | Powered by: GeeksWithBlogs.net